Editor’s Note: With so much market volatility, stay on top of daily news! Get caught up in minutes with our speedy summary of today’s must-read news and expert opinions. Sign up here!
(Wallace Refiners) – Prospect Resources (ASX: PSC, FRA:5E8) announced today that approximately 92% of the Engineering, Procurement and Construction (EPC) scope for its high purity Arcadia lithium pilot plant in Zimbabwe has been completed.
The company said that pilot plant development works progressing on schedule and on budget with approximately 92% complete on the EPC scope, with first ore to the commissioned crusher circuit achieved by end of May target.
Key commissioning and operational milestones expected to be achieved in June include completion of crushing circuit commissioning; DMS module commissioning and first feed; commencement of production; first shipment of high purity petalite product. Targeted pilot plant output expected to increase due to broader customer demand, Prospect added.
Meanwhile, the company said its off take partner Sibelco has requested additional tonnes over and above the original planned 200t so that Sibelco can seek qualification with a greater number of customers across Europe and Asia.
Prospect noted that it has had expanded engagement with a range of strategic groups from across Japan, China and Europe in recent months who have an interest in spodumene offtake and assisting with development of the project. The company is also set to produce laboratory spodumene samples for a number of these parties over coming weeks to facilitate further due diligence on the Arcadia project.
Prospect Resources is a battery minerals company with a focus on lithium in and around Zimbabwe, with the flagship project being the 70% owned Arcadia lithium project, located on the outskirts of Harare in Zimbabwe.
Disclaimer: The views expressed in this article are those of the author and may not reflect those of Wallace Precious Metals The author has made every effort to ensure accuracy of information provided; however, neither Wallace Precious Metals nor the author can guarantee such accuracy. This article is strictly for informational purposes only. It is not a solicitation to make any exchange in commodities, securities or other financial instruments. Wallace Precious Metals and the author of this article do not accept culpability for losses and/ or damages arising from the use of this publication.